Design Meeting Minutes
Summer 2009 Minutes
7/17/2009
Accomplishments
Horizontal Flow Group
Accomplishments
- Reviewed current code for flocculator
- Noted any values that would potentially need to be changed to allow horizontal flow
Issues
- What inhibits the design from just being an 'if' statement that for the most part rotates the tank 90 degrees?
Goals for Upcoming Week
- Meet with Monroe to discuss ideas and more theory behind switch
Floc Hopper Group
Accomplishments
Issues
Goals for upcoming week
Floc Tank Group
Accomplishments
- Discovered that ports are not in fact taking up the whole height of the floc tank, but rather are drawing in the negative direction
Issues
- Baffle spacing is currently too small and must be changed so as to ensure the width and height calculations of the ports come out to be positive
Goals for upcoming week
- Ensure that a minimum baffle spacing is achieved
- Draw slots for the baffles