Floating Floc Meeting Minutes

Spring 2009 Minutes

February 20, 2009

Accomplishments

  • The sand filter group have completely setup the Process Control for their setup.

Metrics

  • The sand filter is almost complete except for an additional hole in the flow acculator for the initial DO probe.

Outcomes

  • The sand filter group will meet on Saturday to start the first run with the new and completed setup.

Issues

  • The sand filter setup need another hole 3/8'' for another DO probe for the initial DO reading.
  •  