Design Goals


Fall 2008 Goals

  1. Overall Goal – continue to improve the automation of the design with built in checks for reasonable values ie. When can sed tank water depth be lowered from the 2m design.
      • Whole Team to be divided as issues are encountered
  2. Aid Honduras Team with individual plant designs as they are presented to us
      • Whole Team to be divided as issues are encountered
  3. Explore other methods of designing the sedimentation tank. Should b be set?
    ***Sara
  4. Adjust baffle placement in the flocculation tank for odd numbered baffles
    ***Tania
  5. Create design pages for sample tanks at different flow rates. For flow rates from 50 gal/min to 1200 gal/min in 100 gal/min increments. Pages will note what portions of the design aren't automated and recommend values.
    ***We will be working in pairs initially for these, but will split off for efficiency in 1 month.
      • To be completed by Oct. 15
  6. Documenting Design Algorithms on the Wiki -
    ***Sara - Lamella, Sedimentation, Slopes, Exit Channel
    ***Tania - Math Functions, Pipe Database, Inlet Channel, Fluids Functions
    ***Cherish - User Inputs, Design Assumptions, Entrance Tank, Minor Loss Coefficients
    ***Reiko - FCM, Fluids Functions, Launder, Sludge Drain