The plan below focuses on the work in Latin America. We need to develop a detailed plan for the project evolution at Cornell also. At Cornell the project can grow to include:
Task |
Location |
Start |
End |
|---|---|---|---|
Document performance of Ojojona |
Honduras |
9/2007 |
ongoing |
Build the water treatment plant at Tamara |
Honduras |
1/2008 |
4/2008 |
Train the Tamara plant operators |
Honduras |
5/2008 |
7/2008 |
Select next candidate communities for construction in Honduras |
Honduras |
2/2008 |
4/2008 |
Document Tamara plant performance |
Honduras |
5/2008 |
|
Honduras |
6/13/2008 |
6/13/2008 |
|
Hire Program Assistant |
Cornell |
7/2008 |
7/2008 |
Identify the funding mechanism for the next communities |
Honduras/Cornell |
6/2008 |
8/2008 |
AguaClara team provides detailed designs for APP selected communities |
Cornell |
6/2008 |
6/2008 |
Task |
Location |
Start |
End |
|---|---|---|---|
Build 3 water treatment plants |
Honduras |
8/2008 |
8/2009 |
New Regional Partners assess potential community sites |
Latin America |
8/2008 |
10/2008 |
Latin America Training Program for engineers and technicians |
Honduras |
9/2009 |
10/2009 |
AguaClara team provides detailed designs for Latin America communities |
Cornell |
10/2008 |
12/2008 |
Latin American partners design plant for first communities |
Latin America |
1/2009 |
2/2009 |
Latin American partners build plant for first communities |
Latin America |
3/2009 |
7/2009 |
Selection process for second launch site |
Global |
2/2009 |
6/2009 |
Hold a regional workshop in Latin America to share experiences and to develop improved strategies.
Send AguaClara Engineers to second launch site. Send team from regional partner at second launch site to Latin America to learn from experiences and to see construction projects and operating AguaClara plants.