Pilot Plant

Team Members

Goals

Organize Pilot Plant wiki (12/12/08)

Fix leaks in plant leveling tank and pipes in order to run tanks. (10/09/08)

Write Midterm Progress Report (10/14/08)

Try to form floc blanket without lamella in second tank to determine if pipe inlet is interfering with blanket formation. (10/19/08)

Construct a new weir for the plant leveling tank so that it can run at 70 m/day (currently, the holes on opposite sides are interfering with eachothers flow). Trim the current weirs to account for increased flow rates through the plant, so that they will not overflow onto the floor. (10/27/08)

Determine whether or not it is possible to form a floc blanket given the current lamella dimensions we have.

Test lamella spacing (11/28/08)

Write Final Report and prepare presentation (12/12/08)