Plate Settler Spacing Team

Fall 2008 Goals

Determine tube diameters to be tested 9/15-10/2
Brainstorm ideas for apparatus 9/15-10/2
Establish a preliminary sketch of apparatus and collaborate with Paul, Matt, Ian, and Professor Weber-Shirk regarding apparatus 10/2
Order materials 10/2
Document experimental apparatus 10/2-forever
Build experimental apparatus 10/2-10/24
Run preliminary experimental trials 10/25-10/31
Run experiment 11/1-11/21
Work-up data and assess results 11/21-12/5
Create new experiment 11/15-end of semester

______

Continuing outside research and designing system Sept 15-19th

Find and order Sedimentation material by Sept 19
Have a testing model by Sept 22
Final working model will be up and running, and we will have our teachin Sept 30,