Sample Lessons Learned Questions

Ron Parks

Questions would be selected based on the type and size of the project

  1. General Processes
  2. Control-Specific
  3. Communications
    Were status and issues communicated in a timely manner to all appropriate parties?
    Did the user community understand the project, what was completed and what was coming next?
  4. Requirements
    Were requirements documented clearly?
    Were specifications clear and well-documented?
    Were test plans adequate?
  5. Overall
    Was the project a success?
    Were project objectives met?
    Be sure to ask for input on "What Went Right"

    Irina Naydich

    Space for Irina

    Greg Bronson

    Space for Greg

    Micci Bogard

    Space for Micci

    Lisa Stensland

    Space for Lisa