Attempt to track current and past work to make the Testing Center more robust. |
Imaged systems now contained within an encrypted file, placed on a thumb drive, to give to Craig for safe-keeping.
Was: 2/10/17: Image all three systems in case of hard drive failure. Might protect against other likelihoods, too.
Request from Craig for recommended action.
Discovered that Brightworks is not available to do this work. (Was: 2/15/17, Oliver contacted Brightworks to see if they might be engaged with this work: Ticket#95300/Physics Testing Center, ensuring robustness in its setup.)
Oliver and Nick Taylor <nwt2> created to-do lists following failing TC1 this week. Either in "Next steps" or "Status reports" (both, above), depending on completion level.