PhysIT staff is doing their best to support the systems in the Testing Center "as is". Invest in reimaging the computers there and ensure networking is optimized to improve PhysIT's capabilities to respond to issues there.

This is part of:

TOC

See also

High-level recommendations

1) Recreate current system on 3 new computers with current operating system and versions of applications.

2) Clarify "system down" procedures for likely scenarios for current set-up (and then new system)

Recommended approach

The current system generally works well so serves as a good model, so focus on recreated it.

Oliver's recommended strategy is to recreate the current system's interrelated functionality using current OS and applications and use that learning to inform possible improvements. Can do this development before investing in new hardware. Deploy into production on new computers. New computers would cost about $650 with 4 year (or more?) warranties, so looking at about $2,000 god for about 4 (5?) years. Keep current scanners, printers, and networking.

Collect improvements desired from Testing Center  and IT Support staff.

Some improvements to consider:

Determine who will lead the project

Review what is known already.

Alan, Nick and other Testing Center staff clearly know a lot regarding not only the necessary desired results, who the technical functions of the system meet those objectives, and all related workflows. Physics IT has made efforts to characterize "what is" from a technical and work-flow perspective:


Next steps

2017-02-10

Nick Taylor (Testing Lab) to dos:

Tech-related work (in priority order)

  1. Determine how daily file-copies are being done from TC2 to TC3. In that case FMPro file copied. Determine how to replicate so copies also going to TC1. And copies from TC1 to TC2 and TC3.
  2. Determine how EZData functions, including dependent helper files, so that it could be reconstructed if on new OS with new version of FM Pro.
  3. Determine how FMPro scripts work so system could be reconstructed or migrated to new version of FM Pro.

Procedures and such

  1. Establish clear procedures for staff to follow if a particular computer or printer is not working.
    1. How much to attempt to fix (answer: very little!). Who to contact (anser: <PhysIT@cornell.edu>). How to do things "by hand", and what to do after system is back up and running.
  2. Question Nick was going to discuss with Alan: Is it worth have a weekly "snapshot" on a USB drive in Alan's office, which would be more "off site"? Worth the added risk?

Status reports

2017-03-09

Imaged systems now contained within an encrypted file, placed on a thumb drive, to give to Craig for safe-keeping.

Was: 2/10/17: Image all three systems in case of hard drive failure. Might protect against other likelihoods, too.

2017-03-01

Request from Craig for recommended action.

2017-02-23

Discovered that Brightworks is not available to do this work. (Was: 2/15/17, Oliver contacted Brightworks to see if they might be engaged with this work: Ticket#95300/Physics Testing Center, ensuring robustness in its setup.)

2017-02-10

Oliver and Nick Taylor <nwt2> created to-do lists following failing TC1 this week. Either in "Next steps" or "Status reports" (both, above), depending on completion level.