Goal

Completion by at least the end of August  (complete this summer). What does success looks like?

Process

To do's

DatePersonTaskNotes
5/20/16Ivan

Review web-hosting services

(Future task: Select and try moving a copy)

5/20/16OliverCreate calendar proposals for check-in meetings every other week, through August, to ensure on-track.Must skip July since Oliver away that month.
    

Completed tasks

Idea: Simply copy completed above items to here, specifying approx. date completed.

Completion date (approx)Original datePersonTaskNotes
     

Meeting notes (reverse chron)

5/20/16 Fri

Oliver and Ivan met. Reviewed Oliver's queries to CIT (IWS and CIT's AWS/ Docker folks).

Ivan can't afford web developer work so re-write not appropriate.

Learning Docker and associated abstraction layers also does not seem appropriate.

Instead, look for server hosting to host current Perl-based application (with server-side includes) such that someone else is maintaining current:

We hope a migration "just works" with minimal input from Ivan. Oliver's concern is that this won't be a slam-dunk migration due to age of code (deprecated functions, etc) and configuration difference. Bluehost has experience with users doing this, and have written to this point here: