PhysIT (via ChemIT) begins service to Physics Admin and Instruction Nov. 1st, 2013. This page identifies activities and their status related to transition service from CCMR/ LASSP.

Cross-reference:

Documentation for Physics Administration and Instruction

Notes

Web site run out of the Linux Lab

Migration summary and status

Information panel to review with John Miner.

Migration or transition area

Time/
Timing

Cost

Status

Notes

Move FileMakerPro files from Barry's server to the A&S server.

Q: Able to do sooner than later? (Since dependent on Barry's server.)

 

PhysIT to look over current files and develop a proposal for John.

Option 1: Move server to PhysIT, temporarily. Less disruption, less risk. Then migrate to A&S's FMPro server.
Option 2: Migrate to A&S's FMPro server.

Review "Opportunities for improvement". For example:
ID Finder, securing the network, computer upgrades, support of select systems and software in Nick's area.

 

 

On-going.

Although associated proposals and tasks are technically not required for migration from Barry, some task may warrant consideration or action earlier than later.