NSF grant awarded. Thus, this is a "go" as of August 2013.

Notes for Hoffmann cluster researchers

Upcoming to do's for your researchers:

(1) Ensure researchers' user data on Sol can be completely deleted.

2) After a predetermined date, researchers will not have access to Sol until it is again ready for testing.

3) Researchers will be asked to test select software on Sol.

Oliver's quick notes:

11/15/13, from email sent to Roald, by Oliver:

The rest of the email:

I believe we have a short-term answer to address your group's need for the Intel compiler. This temporary solution will work as long as we are earnestly working on a long-term solution.

When you return, I would appreciate discussing options to meet your long-term needs cost-effectively. Michael Hint and I have some imaginative ideas, but some involve coordinating with other CCB researchers (Scheraga and Ananth).

Michael Hint learned the difference between a single user license and the 2-person concurrent licenses. The answer (below) informs one of our ideas, if you care to read it before we meet. But no problem if you don't get to it since I  can summarize when I discuss our ideas.

==================================

Sent: Friday, November 08, 2013 4:00 PM
To: Guoying Gao
Cc: Oliver B. Habicht
Subject: one computer matter which will come up

Hi, Guoying,

               In his conversation with me, Oliver said that he has investigated the error message referring to absence of a license for an Intel Compiler. It indeed appears that we had been using an older compiler, and that to use it in the future we will need to get a license. But that license is costly; Oliver is determining how much. What he will ask you, and you might inquire of the group in preparation is how often we use that compiler – daily, once a week, once a year? And how many people in the group are using it.

Thanks,

roald

==================================

Next steps

Draft idea

Unknowns

Tasks and estimated timing

Top Level Task Description

Effort Est.

Assignee

Planning

 

 

Discovery/ Overview mtg

1.5 hrs

 

Vet options and conduct needs analysis to match to hardware order

1-2 weeks

 

Specify exactly the systems to order within budget. Includes iterating with vendor experts.

1 week

 

Approval

0 days

 

Order & Installation

 

 

Place & Process order

1/2 week

 

Delivery, after order is placed at Cornell

~3 weeks

 

Receive order and set-up hardware in 248 Baker Lab

1 week

 

Build New Cluster

 

 

Get head node and 1st cluster node operational with OS and cluster management software

3 weeks

 

Test / Verify / Approval

1 week

 

Convert Old Cluster

 

 

Move user accounts and data; test, prep, and do

1 week

 

Move old nodes to new cluster

1 week

 

Other provisioning models and related ideas

Buy cycles, on demand

Good for irregular high-performance demands, especially if have high peaks of need and long-lasting jobs.

Host hardware at CAC rather than with ChemIT

Hosting costs at CAC is for basic: Expert initial configuration, then keep the system current, and keep the lights running. Other service charged hourly.

Per the above rate calculator, the rate for 9 nodes (1 head node + 8 compute nodes) would be $8,291/yr. Or, $24,873 for 3 years for this service.

At current ChemIT rates, 9 nodes would be $321.84/yr. Or, $965.52 for 3 years of service.

Table, related to our options

                          Option ==>
Consideration, below:

ChemIT

CAC:
RedCloud

CAC:
Hosting

Amazon (EC3?) or
Google (Compute?)

Other ideas?

Hardware costs

$25K

-

$25K

-

 

Hardware support

Yes.

-

Yes.

-

 

OS install and configuration

Yes. CentOS 6.4

 

Yes. CentOS 6.4

 

 

Cluster and queuing management

Yes. Warewulf, with options

-

Yes. ROCKS, no options.

-

 

Research software install and configuration

Yes

No

Yes; additional cost

No

 

Application debugging and optimization support

Not usually.
Available from CAC, at additional cost?

Yes; additional cost

Yes; additional cost

No.
Available from CAC, at additional cost?