NSF grant awarded. Thus, this is a "go" as of August 2013. |
Upcoming to do's for your researchers:
2) After a predetermined date, researchers will not have access to Sol until it is again ready for testing.
Sol will need to be turned off and worked on by us. (Approximate duration?) Therefore, it will be off-line to researcher.
Ad hoc permission to select researches (Prasad?) will be granted so they may install and test their software.
Tasks for us to do:
* Get the server's versioning hard disk recognized within the new head node.
* Lulu to install the Intel compiler in the /software/ directory, with the proper licensing.
* Your group (Prasad?) to install the Materials Studio software in the /data/ Hoffmann/bin/ directory. If Prasad is not available to do this, let's discuss our options- thank you.
3) Researchers will be asked to test select software on Sol.
Changes to where the Intel compiler and Materials Studio reside (to facilitated debugging and support) must be confirmed to work for researchers.
Again we are testing on Sol. Thus, the only production work should still be on Helios, not Sol.
11/15/13, from email sent to Roald, by Oliver:
The rest of the email:
I believe we have a short-term answer to address your group's need for the Intel compiler. This temporary solution will work as long as we are earnestly working on a long-term solution.
When you return, I would appreciate discussing options to meet your long-term needs cost-effectively. Michael Hint and I have some imaginative ideas, but some involve coordinating with other CCB researchers (Scheraga and Ananth).
Michael Hint learned the difference between a single user license and the 2-person concurrent licenses. The answer (below) informs one of our ideas, if you care to read it before we meet. But no problem if you don't get to it since I can summarize when I discuss our ideas.
==================================
Sent: Friday, November 08, 2013 4:00 PM
To: Guoying Gao
Cc: Oliver B. Habicht
Subject: one computer matter which will come up
Hi, Guoying,
In his conversation with me, Oliver said that he has investigated the error message referring to absence of a license for an Intel Compiler. It indeed appears that we had been using an older compiler, and that to use it in the future we will need to get a license. But that license is costly; Oliver is determining how much. What he will ask you, and you might inquire of the group in preparation is how often we use that compiler – daily, once a week, once a year? And how many people in the group are using it.
Thanks,
roald
==================================
Top Level Task Description |
Effort Est. |
Assignee |
|---|---|---|
Planning |
|
|
Discovery/ Overview mtg |
1.5 hrs |
|
Vet options and conduct needs analysis to match to hardware order |
1-2 weeks |
|
Specify exactly the systems to order within budget. Includes iterating with vendor experts. |
1 week |
|
Approval |
0 days |
|
Order & Installation |
|
|
Place & Process order |
1/2 week |
|
Delivery, after order is placed at Cornell |
~3 weeks |
|
Receive order and set-up hardware in 248 Baker Lab |
1 week |
|
Build New Cluster |
|
|
Get head node and 1st cluster node operational with OS and cluster management software |
3 weeks |
|
Test / Verify / Approval |
1 week |
|
Convert Old Cluster |
|
|
Move user accounts and data; test, prep, and do |
1 week |
|
Move old nodes to new cluster |
1 week |
|
Good for irregular high-performance demands, especially if have high peaks of need and long-lasting jobs.
Hosting costs at CAC is for basic: Expert initial configuration, then keep the system current, and keep the lights running. Other service charged hourly.
Per the above rate calculator, the rate for 9 nodes (1 head node + 8 compute nodes) would be $8,291/yr. Or, $24,873 for 3 years for this service.
At current ChemIT rates, 9 nodes would be $321.84/yr. Or, $965.52 for 3 years of service.
Option ==> |
ChemIT |
CAC: |
CAC: |
Amazon (EC3?) or |
Other ideas? |
|---|---|---|---|---|---|
Hardware costs |
$25K |
- |
$25K |
- |
|
Hardware support |
Yes. |
- |
Yes. |
- |
|
OS install and configuration |
Yes. CentOS 6.4 |
|
Yes. CentOS 6.4 |
|
|
Cluster and queuing management |
Yes. Warewulf, with options |
- |
Yes. ROCKS, no options. |
- |
|
Research software install and configuration |
Yes |
No |
Yes; additional cost |
No |
|
Application debugging and optimization support |
Not usually. |
Yes; additional cost |
Yes; additional cost |
No. |
|