NSF grant awarded, so this is a "go", August 2013

Next steps

Draft idea

High-level overview

Unknowns

Tasks and estimated timing

Top Level Task Description

Effort Est.

Assignee

Planning

 

 

Vet options and conduct needs analysis to match to hardware order

1-2 weeks

 

Specify exactly the systems to order within budget. Includes iterating with vendor experts.

1 week

 

Order & Installation

 

 

Place & Process order

1/2 week

 

Delivery, after order is placed at Cornell

~3 weeks

 

Receive order and set-up hardware in 248 Baker Lab

1 week

 

Build New Cluster

 

 

Get head node and 1st cluster node operational with OS and cluster management software

3 weeks

 

Test / Verify / Approval

 

 

Convert Old Cluster

 

 

Move user accounts and data

 

 

Move old nodes to new cluster

 

 

 

 

 

Lulu becomes available ~mid-September?

See unknowns, above, which related to tasks which will obviously take additional time to accomplish.

Other ideas

Buy cycles, on demand.

Good for irregular work, especially if have high peaks of need.

Table

Option:

ChemIT

CAC:
RedCloud

CAC:
Hosting

Amazon (EC3?) or
Google (Compute?)

Other ideas?

Hardware costs

$25K

-

$25K

-

 

Hardware support

Yes.

-

Yes.

-

 

OS install and configuration

Yes. CentOS 6.4

 

Yes. CentOS 6.4

 

 

Cluster and queuing management

Yes. Warewulf, with options

-

Yes. ROCKS, no options.

-

 

Research software install and configuration

Yes

No

Yes; additional cost

No

 

Application debugging and optimization support

Not usually.
Available from CAC, at additional cost?

Yes; additional cost

Yes; additional cost

No.
Available from CAC, at additional cost?