NSF grant awarded, so this is a "go", August 2013

Next steps

Draft idea

High-level overview

Unknowns

Tasks and estimated timing

Top Level Task Description

Effort Est.

Assignee

Planning

 

 

Vet options and conduct needs analysis to match to hardware order

1-2 weeks

 

Specify exactly the systems to order within budget. Includes iterating with vendor experts.

1 week

 

Order & Installation

 

 

Place & Process order

1/2 week

 

Delivery, after order is placed at Cornell

~3 weeks

 

Receive order and set-up hardware in 248 Baker Lab

1 week

 

Build New Cluster

 

 

Get head node and 1st cluster node operational with OS and cluster management software

3 weeks

 

Test / Verify / Approval

 

 

Convert Old Cluster

 

 

Move user accounts and data

 

 

Move old nodes to new cluster

 

 

 

 

 

Lulu becomes available ~mid-September?

See unknowns, above, which related to tasks which will obviously take additional time to accomplish.