NSF grant awarded, so this is a "go", August 2013 |
Next steps
- Meet to review all options and confirm desired direction and expected timing.
- Review resources. Xiao-Qiu Ye has cluster experience, including set-up.
Draft idea
High-level overview
- Create a stand-along cluster using new hardware ($25K).
- Uses new OS and related cluster management software.
- Install and configure necessary applications.
- Enable NetID-based access, if possible (limit 2-3 days for a "go/no-go" decision on this functionality)
- Confirm old nodes can successfully be added to that new cluster.
- Migrate users to new cluster.
- Migrate old nodes to new cluster.
Unknowns
- Time for install of all necessary applications, many of which are new to Lulu.
- Whether NetID-based access will succeed. But note that this is not a do-or-die step.
Tasks and estimated timing
Vet options and conduct needs analysis to match to hardware order
Specify exactly the systems to order within budget. Includes iterating with vendor experts.
Place order
Delivery, after order is placed at Cornell
Receiving order and set-up in 248 Baker Lab
Get head node and 1st cluster node operational with OS and cluster management software
- 3 weeks
- Lulu becomes available ~mid-September?
See unknowns, above, which related to tasks which will obviously take additional time to accomplish.
Other ideas
- Rent from CAC.
- Walk through rates and scenarios.