Team Precipitation
Fall 2008 Minutes
10.23.08
Accomplishments
- Determined a process for fixing the chlorine tank bulkhead fittings.
- Run more settling and float valve flow restriction experiments.
Metrics
- Schedule a meeting time with Monroe.
- Contract John Guest about current bulkhead fittings and ask about possibilities for the future.
Issues
- When we attempt to measure weight of settled calcium carbonate the filter papers continually clog.