Sample Lessons Learned Questions

Ron Parks

Questions would be selected based on the type and size of the project

  1. General Processes
    • What would you say were the most critical factors for project success?
    • Which tools or techniques worked well?
    • Were there organizational obstacles that made it difficult to complete the project
    • Were roles and responsibilities clearly defined?
  2. Control-Specific
    • Have any scope changes to this project impacted the schedule? How?
    • Have cross-project dependencies affected scope? How?
    • Was the work plan well documented, with appropriate structure and detail?
    • Did stakeholders have appropriate input into the project planning process?
    • How often were deliverables 're-worked' based on the introduction of new requirements?
    • Were deliverables 're-worked' because they did not meet requirements?
    • Were communications adequate in all activities?
    • Was risk controlled adequately?
    • Was an adequate contingency plan created?
    • Did the project meet all original scheduled milestones/deadlines?
    • Was project status reported according to plan?
    • Were all issues resolved in a timely manner?
    • Did the change control procedure work adequately?
    • Did the project receive all the necessary approvals to proceed in a timely fashion?
    • Was the project staffed appropriately?
    • Was quality of the product or services adequate?
    • Were Initial cost and schedule estimates were accurate?
    • Was the technology solution chosen appropriate for the project?
  3. Communications
    • Were status and issues communicated in a timely manner to all appropriate parties?
    • Did the user community understand the project, what was completed and what was coming next?
  4. Requirements
    • Were requirements documented clearly?
    • Were specifications clear and well-documented?
    • Were test plans adequate?
  5. Overall
    • Was the project a success?
    • Were project objectives met?
    • Be sure to ask for input on "What Went Right"