Gantt Chart for David Mcevoy
|| Gantt Chart || Feb || || || March || || || || April || || || || || May || ||
|| Week: || 11 || 18 || 25 || 3 || 10 || 17 || 24 || 1 || 7 || 14 || 21 || 28 || 5 || 12 ||
| Channel Hole reconstruction | work | | | | | | | | | | | | | | |
| Sludge Removal | work | work | | | | | | | | | | | | |
| Baffle Re-fitting | | work | work | | | | | | | | | | | | |
| Run Data Collection | | | | | | | work | work | work | work | work | work | work | work |
| Build Tube Settler support device | | | | | work | | | | | | | | | | |
| Re-rout turbidity inflow and out flow tubes | | | work | work | | | | | | | | | | | |
| Install Pressure head device to fix O2 saturation | | | work | | | | | | | | | | | | |
| Do write up on pressure head design/construction | | | work | | | | | | | | | | | | |
| Install Auto flow device to front end of the floc tank | | | work | work | work | | | | | | | | | | |
| Design Sed Tank | | | | | work | | work | work | | | | | | | |
| Incorporate Auto. Chem Feed into Pilot Plant | | work | work | work | work | | | | | | | | | | |
| Incorporate Sed Tank into Pilot Plant | | | | | work | | work | work | work | work | work | work | work | work |
| Add Obstruction to Flow Channels | | | | | | | | work | work | work | work | work | work | work |
| Improve testing procedure | | | | | | | | work | work | work | work | work | work | work |
| Assist with Data Analysis | | | | | | | | work | work | work | work | work | work | work |
| Write Sedimentation Report | | | | | | | | | | | | | work | work | work |
| Write Report on Tapered Flocculation | | | | | | | | | | | | | work | work | work |
| Write Report on Obstructions | | | | | | | | | | | | | work | work | work |