Accomplishments
- The sand filter group have completely setup the Process Control for their setup.
- Final decision on the setup for the relevant literature page: Title, Summary, Link to URL or PDF.
Metrics
- The sand filter is almost complete except for an additional hole in the flow accumulator for the initial DO probe.
- Calibrated the two DO probes for the sand filter setup to measure the DO content before and after the water flow through the sand layer.
- Completion of the diagram of the sand filter.
Outcomes
- The sand filter group will meet on Saturday to do the first run with the new and completed setup.
Issues
- The sand filter setup need another hole 3/8" for another DO probe for the initial DO reading.