  • Pull an old Compute Node (CN) and convert to a new CentOS Head Node ("new HN"“new HN”)
  • Add new CNs to new HN
  • Add one old CN's CN’s to new HN
  • After testing, shift production to new HN.
  • Add the rest of the old CN's CN’s to new HN
  • Convert old HN to CN and add it to new HN
  • Later; see P41: Migrate to ChemIT Community Head Node
    • Add all CN's CN’s to ChemIT Community HN
    • Convert Collum HN to CN and add to ChemIT Community HN

...

  • If so, use another node (for example, 3).

Time and labor estimates

View Project timeline: Collum Cluster timeline.pdf

Est. labor: ~286 hours

Duration - Start-to-finish time (taking into account availability): 30 work days (start 7/31, Wed)

...