Design Team

...

Meeting Minutes

Spring 2009 Minutes

"Date"

...

Friday, March 6, 2009

Accomplishments
  • A summary of major work completed since last meeting based on last meeting's identified outcomes/issues
  •  
Metrics
  • Quantitative and qualitative results from accomplishments and outcomes.
  • Potential metrics for unresolved issues.
Outcomes
  • A summary of resolutions based on what was accomplished.
  • New directions and ideas that result from these resolutions.
Issues
  • Difficult and unresolved issues
  • Plans for action

Working Group: 2

Accomplishments
  • A summary of major work completed since last meeting based on last meeting's identified outcomes/issues
  •  
Metrics
  • Quantitative and qualitative results from accomplishments and outcomes.
  • Potential metrics for unresolved issues.
Outcomes
  • A summary of resolutions based on what was accomplished.
  • New directions and ideas that result from these resolutions.
Issues
  • Difficult and unresolved issues
  • Plans for action
  • Started the process of changing algorithms based on energy dissipation rate instead of G*theta.
  • Worked on flocculator energy dissipation program.
Metrics
  • Gracias preliminary design (Excel spreadsheet) with preliminary parameters.
Outcomes
  • For this week, divided tasks included: Change flocculator energy dissipation  program back to handle  arrays so that we can have uniform and tapered baffle spacing as well as Fix the placement code for the baffles, Change drain so that the pipe is now a rectangular channel, Change inlet "pipes" so that they are inlet rectangular columns, Modify the slopes program, Adjust the entrance tank so that the dimensions of the tank are specified based on an entrance tank upward velocity.
Issues
  • Continue updating and checking for the name variable changes.

...