(Table started November 2015)
| Group | MonthsGroups | Default day and time of day | First warning email sent when | Second warning email sent when | Notes | Next Scheduled downtime||
|---|---|---|---|---|---|---|---|
| Abruna | March | 1 | 1st Wednesday of the month 9:30am | 2 weeks before | 24 hours before | Need do cluster upgrade, may merge with Widom-Loring? | TBD|
| Collum | March | 1st Monday of the month (if holiday, move to 1st Tuesday) 9:30am | 2 weeks before | 24 hours before | TBD | ||
| Hoffmann | March | 2 | 3nd 2nd Tuesday of the month 9:30am | 2 weeks before | 24 hours before | Changed to morning | TBD|
| Lancaster (w/ Crane) | March | 3rd Monday Wednesday of the month 9:30am | 2 weeks before | 24 hours before | TBD | ||
| Scheraga | March | 1 | 2rd 3rd Wednesday of the month 9:30am | 2 weeks before | 24 hours before | TBD | |
| Widom-Loring-Collum | March | 3 | 1st Tuesday 1st Thursday of the month 9:30am | 2 weeks before | 24 hours before | TBD | |
| Eldor | March | 2nd Thursday of the month 9:30am | 2 weeks before | 24 hours before | TBD |
| Groups | Group member | Next Scheduled Downtime | Following Scheduled Downtime |
|---|---|---|---|
| 1 | Abruna Scheraga | June 1st June 8th | Sept 7th Sept 14th |
| 2 | Collum Hoffmann | July 18th July 26th | Oct 3rd Oct 18th |
| 3 | Widom-Loring-Collum Eldor Lancaster (w/ Crane) | Aug 2nd Aug 11th Aug 17th | Nov 1st Nov 10th Nov 16th |