8/27/13Tue: Oliver met with Brian Crane
- Brian Crane agreed to wait for us to start and focus on Hoffmann's new cluster.
- Crane will email Kyle Lancaster with an update. Plan is to move forward with retrofit of Lancaster's cluster, pending Kyle's approval.
- Oliver to meet with Kyle to review steps and timing in more detail.
- Having come close to completing Collum's cluster retro-fit, Oliver estimates 8 Lulu being able to start in ~8 weeks. BUT, must start we can and should start work with Brian and designates much earlier (4 weeks earlier!) to spec and order hardware to so it can be be ready for Lulu to start work with in 8 ~8 weeks.
- Oliver to provide Crane a status report every 2-3 weeks., until we start
Previously shared activity and ideas
From ~3/13:
1) CRCF to advise on what system would work. Do within 2 weeks of 3/4/13. RedBarn and Dell. Informed by applications used. ~$5K.
...