Top Level Task Description

Effort Est.

Assignee

Planning

 

 

Discovery/ Overview mtg

1.5 hrs

 

Vet options and conduct needs analysis to match to hardware order

1-2 weeks

 

Specify exactly the systems to order within budget. Includes iterating with vendor experts.

1 week

 

Approval

0 days

 

Order & Installation

 

 

Place & Process order

1/2 week

 

Delivery, after order is placed at Cornell

~3 weeks

 

Receive order and set-up hardware in 248 Baker Lab

1 week

 

Build New Cluster

 

 

Get head node and 1st cluster node operational with OS and cluster management software

3 weeks

 

Test / Verify / Approval

1 week 

 

Convert Old Cluster

 

 

Move user accounts and data
; test, prep, and do

1 week  

 

Move old nodes to new cluster

 

1 week 

 

 

 

  • Lulu becomes available ~mid-September

...

  • or early Oct, as of 8/21/13.
  • See unknowns, above, which related to tasks which will obviously take additional time to accomplish.

Other provisioning models and related ideas

...