Top Level Task Description | Effort Est. | Assignee | |||
|---|---|---|---|---|---|
Planning |
|
| |||
Discovery/ Overview mtg | 1.5 hrs |
| |||
Vet options and conduct needs analysis to match to hardware order | 1-2 weeks |
| |||
Specify exactly the systems to order within budget. Includes iterating with vendor experts. | 1 week |
| |||
Approval | 0 days |
| |||
Order & Installation |
|
| |||
Place & Process order | 1/2 week |
| |||
Delivery, after order is placed at Cornell | ~3 weeks |
| |||
Receive order and set-up hardware in 248 Baker Lab | 1 week |
| |||
Build New Cluster |
|
| |||
Get head node and 1st cluster node operational with OS and cluster management software | 3 weeks |
| |||
Test / Verify / Approval | 1 week |
| |||
Convert Old Cluster |
|
| |||
Move user accounts and data | 1 week |
| |||
Move old nodes to new cluster |
| 1 week |
|
|
|
- Lulu becomes available ~mid-September
...
- or early Oct, as of 8/21/13.
- See unknowns, above, which related to tasks which will obviously take additional time to accomplish.