Top Level Task Description | Effort Est. | Assignee |
|---|---|---|
Planning |
|
|
Vet options and conduct needs analysis to match to hardware order | 1-2 weeks |
|
Specify exactly the systems to order within budget. Includes iterating with vendor experts. | 1 week |
|
Order & Installation |
|
|
Place & Process order | 1/2 week |
|
Delivery, after order is placed at Cornell | ~3 weeks |
|
Receive order and set-up hardware in 248 Baker Lab | 1 week |
|
Build New Cluster |
|
|
Get head node and 1st cluster node operational with OS and cluster management software | 3 weeks |
|
Test / Verify / Approval |
|
|
Convert Old Cluster |
|
|
Move user accounts and data |
|
|
Move old nodes to new cluster |
|
|
|
|
|
Lulu becomes available ~mid-September?
...