Comment: Changed top level task to table, added additional steps

...

Tasks and estimated timing

Top Level Task Description

Effort Est.

Assignee

Vet options and conduct needs analysis to match to hardware order

1-2 weeks

 

Specify exactly the systems to order within budget. Includes iterating with vendor experts.

1 week

 

Place & Process order

1/2 week

 

Delivery, after order is placed at Cornell

~3 weeks

 

...

Receive order and set-up hardware in 248 Baker Lab

1 week

 

Get head node and 1st cluster node operational with OS and cluster management software

3 weeks

 

Test / Verify / Approval

 

 

Move user accounts and data

 

 

Move old nodes to new cluster

 

 

Lulu becomes available ~mid-September?

See unknowns, above, which related to tasks which will obviously take additional time to accomplish.

...