Work descriptions

Effort
in Hours or days

Elapse time
(usually days or weeks)

Est. date

Install and config CentOS on headnode
(Use Node 2)

3 days

1 week

 

Install and config Warewulf
Includes attaching one (new) node

5 days

1 week

 

Install and config Torque / maui

2 days

.5 wk

 

Install and config WebMO

5 days

1 week

 

Install and config 2nd (new) node
and 3rd (old) node.

1 day

.2 week

 

Copy Jun data for test

2 days

.5 wk

 

Jun (and group) test & tweak

2 days

1 week


Cleanup / additional

2 days

.5 wk

 

Move old cluster nodes to new Cluster
Keep the old head node for 1 month?

1 day

.2 wk

 

Move old cluster user data to new cluster
(Collum group down time)

2 - 3 days

.5 week

 

 

Total

18 25 days

5 6.7 4 weeks


 

 

 

 

Plan

See above work descriptions for detailed steps.

...