Est. labor: ~110 hours for Lulu, plus Michael's hours for networking, hardware configuration, consultation, etc.

Work descriptions

Effort
(usually hours; 1 day = 6 hours @ 75%)
Lulu, unless otherwise indicated in Hours or days

Elapse time
(usually days or weeks)

Est. date

Install and config CentOS on headnode
(Use Node 2)

3 days

1 week

 

Install and config Warewulf
Includes attaching one (new) node

5 days

1 week

 

Install and config Torque

2 days

.5 wk

 

Install and config WebMO

5 days

1 week

 

Install and config 2nd (new) node
and 3rd (old) node.

1 day

.2 week

 

Copy Jun data for test

 

 

 

Jun et al. test & tweak

2 days

1 week
End of August


Cleanup / additional

 

 

 

Move old nodes to new Cluster

 

 

 

Move user data to new cluster

 

 

 

 

Total

18 days

5.7 weeks

 

 

 

 

Plan

See above work descriptions for detailed steps.

...