CCMR's web service shuts down and Freed's web site continues to work correctly.
Project status
4/15/13 Monday: Oliver observed that both the original production and new staging web sites look very similar.4/5/13: The copy of web site is on CIT-hosted web server. All technologies seem to be working correctly on the new location, but must be further confirmed by Dee. Dee can connect and modify items in the new location.
...
Migration to CIT's LAMP service
April 15, 2013, Monday: Oliver wrote to Curt requesting time estimate for cut-over, with link to above to-do's. And the work required if cut-over not for this week.
April 5, 2013, Friday: Oliver sent Curt a copy of this project's current status and to-do's, asking for time-frames for to-do's leading up to the domain name change Barry will need to do. Requested time-frame estimates within a week or so.
...