Design team Meeting Minutes" Meeting Minutes
Spring 2009 Minutes
"2/20/09"
Working Group: 1
Accomplishments
- A summary of major work completed since last meeting based on last meeting's identified outcomes/issues
Metrics
- Quantitative and qualitative results from accomplishments and outcomes.
- Potential metrics for unresolved issues.
Outcomes
- A summary of resolutions based on what was accomplished.
- New directions and ideas that result from these resolutions.
Issues
- Difficult and unresolved issues
- Plans for action
Working Group: 2
Accomplishments
- A summary of major work completed since last meeting based on last meeting's identified outcomes/issues
Metrics
- Quantitative and qualitative results from accomplishments and outcomes.
- Potential metrics for unresolved issues.
Outcomes
- A summary of resolutions based on what was accomplished.
- New directions and ideas that result from these resolutions.
Issues
- Difficult and unresolved issues
- Plans for action
...
Accomplishments
- Went over Monroe's MathCAD algorithm
Outcomes
- Sara updated variables and parameters for the Gracias plant.
- Reviewed and updated team goals list based on Nicole's comments.
- Heather R & Adela continue working on a design for Gracias.
- Reiko & Heather H continue working on a design for the Ecuador plant.